The University of California has committed to buying 20 percent of its grid-purchased electricity from renewable sources by 2010 and to generating 10 megawatts of onsite renewable electricity by 2014.

UCSD's Novel Efforts to Go Green
From Science Today ›

Onsite renewable energy installations

Campus Technology & capacity (kw) Status Start date
Agriculture & Natural Resources - Kearny PV (23) Under construction 8/2012
Berkeley PV (100) Installed 11/2003
Davis PV (782) Installed/ Under Construction 12/2011
Davis (West Village) PV (4,000) Installed/Under Construction 1/2012
Davis Health System PV (145) Under Construction 1/2012
Irvine PV (895) Installed 1/2009
Irvine PV (136) Installed 3/2011
Merced PV (1000) Installed 1/2010
San Diego PV (1330) Installed 7/2011
San Diego PV (995) Under Construction 4/2012
San Diego PV (150) Planned 4/2012
San Francisco PV (250) Installed 1/2008
San Francisco PV (250) Planned 7/2012
Santa Barbara PV (550) Design 6/2012
Santa Barbara PV (225) Installed 12/2008
Santa Cruz PV (200) Design 6/2012
Los Angeles Biogas from landfill used in CHP plant (3,500) Installed 1990s
San Diego Biogas from wastewater treatment facility used in fuel cell (2,800) Installed 11/2011